IMPORTANT INFORMATION:
Robin Meadows Roofing Project Letter | Roofing FAQ
Preparing for your new roof | Door notification
- 41% OF THE ROOFING PROJECT IS COMPLETE: To date, three triplexes and 10 single-family homes have been completed. 19 of 46 roofs (41%) have been finished. Please take a look at your home and note any issues with pictures and an e-mail to the board.
- CONTINGENCY BUDGET: Through the first 14 homes, we spent $10,279.24 on contingencies which is $3,721.76 under budget. Almost half of the contingencies were from the 3169/3171/3173 triplex ($4,943.62). Only one other home (3179) was over budget on a per-home basis ($1,934.82). These four homes accounted for over 67% of the contingency spending.
- DRIVEWAY ACCESS: Cooper Mountain will need full access to your driveway while working on your roof. Please move all vehicles from your driveway to protect your vehicle and facilitate your roofing being replaced in a timely manner.
- WEATHER: Remember that roofing is weather-dependent. Rain, extreme heat, or smoke from wildfires can delay the work.
- REPLACEMENT SCHEDULE: The following is the tentative order of roof replacement. Weather, crew availability, material delivery, and other factors may alter the schedule. Owners will be notified several days before hand of material delivery and/or work beginning on their home.
1. 3211/3213/3215 (DONE, 5/27),
2. 3169/3171/3173 (DONE, 6/6), 3151/3153/3157 (DONE, 6/14)
3. 3179 (DONE, 6/14), 3181 (DONE, 6/13), 3187 (DONE, 6/12), 3189 (DONE, 6/8), and 3201 (DONE, 6/13)
4. 3203 (DONE, 6/12), 3205 (DONE, 6/12)
5. 3125, 3127, 3129 (MATERIAL DELIVERED, 6/16) , 3027, 3130, 3132 (DONE, 6/18)
6. 3071, 3073, 3077/3079/3081, 3085, 3087 (CURRENTLY BEING WORKED ON, 6/19)
7. 3170/3168, 3162, 3160, 3167, 3165 (MATERIAL DELIVERED, 6/24)
8. 3084, 3082, 3078, 3076, 3074
9. 3206/3204/3202, 3214/3212/3210