Roofing project update – 6/10/25

Two triplexes and one single family home have been completed.

IMPORTANT INFORMATION:
Robin Meadows Roofing Project Letter | Roofing FAQ
Preparing for your new roof | Door hanger notification


  • SECOND TRIPLEX COMPLETE: A second triplex (3169/3171/3173) is complete. Fifty pieces of plywood had to be replaced, along with some soffit plywood. We anticipate this to be the most plywood needing to be replaced as this triplex had the most leaks. Our first single-family home (3189) has been completed, while 3181, 3187, and 3201 are currently being worked on. Please take a look at your home and note any issues with pictures and an e-mail to the board.

  • DRIVEWAY ACCESS: Cooper Mountain will need full access to your driveway while working on your roof. Please move all vehicles from your driveway to protect your vehicle and facilitate your roofing being replaced in a timely manner.

  • WEATHER: Remember that roofing is weather-dependent. Rain, extreme heat, or smoke from wildfires can delay the work.

  • REPLACEMENT SCHEDULE: The following is the tentative order of roof replacement. Weather, crew availability, material delivery, and other factors may alter the schedule. Owners will be notified several days before hand of material delivery and/or work beginning on their home.


1. 3211/3213/3215 (DONE, 5/27),
2. 3169/3171/3173 (DONE, 6/6), 3151/3153/3157 (MATERIAL DELIVERED, 6/3; started 6/11)
3. 3179, 3181, 3187, 3189 (DONE, 6/8), and 3201 (MATERIAL DELIVERED, 5/28)
4. 3203, 3205 (MATERIAL DELIVERED,5/28)
5. 3125, 3127, 3129, 3027, 3130, 3132 (MATERIAL DELIVERED, 6/10)
6. 3071, 3073, 3077/3079/3081, 3085, 3087
7. 3170/3168, 3162, 3150, 3167, 3165
8. 3084, 3082, 3078, 3076, 3074
9. 3206/3204/3202, 3214/3212/3210