- FIRST TRIPLEX COMPLETE: The roofing of 3211/3212/3213 triplex has been completed. Three sheets of plywood and two pieces of fascia were replaced, resulting in the project being under budget for plywood/wood replacement. Please take a look and note any issues with pictures and an e-mail to the board.
- WORK STARTED ON SECOND TRIPLEX: Work on the 3169/3171/3173 triplex started on 5/28/25. This building has had the most leaks over the years, and we expect it to require the most plywood replacement. Twenty-five sheets of plywood have had to be replaced and five soffit plywood boards.
- SECOND CREW ON SITE: A second crew joined the work on 6/3/2025 and started on 3189.
- REPLACEMENT SCHEDULE: The following is the tentative order of roof replacement. Weather, crew availability, material delivery, and other factors may alter the schedule. Owners will be notified several days before hand of material delivery and/or work beginning on their home.
1.3211/3213/3215 (DONE, 5/27),
2. 3169/3171/3173 (STARTED, 5/28), 3151/3153/3157
3. 3179, 3181, 3187, 3189, and 3201 (MATERIAL DELIVERED, 5/28 | STARTED, 6/3)
4. 3203, 3205
5. 3125, 3127, 3129, 3027, 3130, 3132
6. 3071, 3073, 3077/3079/3081, 3085, 3087
7. 3170/3168, 3162, 3150, 3167, 3165
8. 3084, 3082, 3078, 3076, 3074
9. 3206/3204/3202, 3214/3212/3210 - DRIVEWAY ACCESS: Cooper Mountain will need full access to your driveway while working on your roof. Please move all vehicles from your driveway to protect your vehicle.
- WEATHER: Remember that roofing is weather-dependent. Rain, extreme heat, or smoke from wildfires can delay the work.
Images from the roof of the 3169/3171/3173 triplex.