- 99% OF THE ROOFING PROJECT IS COMPLETE: To date, seven triplexes, one duplex, and 24 single-family homes have been completed. All 46 have been finished. A final walk-through will be scheduled, and the final bill will be paid which will conclude the project.
Please take a look at your home and note any issues with pictures and an e-mail to the board. - REPLACEMENT SCHEDULE: The following is the tentative order of roof replacement. Weather, crew availability, material delivery, and other factors may alter the schedule. Owners will be notified several days in advance of material delivery and/or work beginning on their home.
1. 3211/3213/3215 (DONE, 5/27),
2. 3169/3171/3173 (DONE, 6/6), 3151/3153/3157 (DONE, 6/14)
3. 3179 (DONE, 6/14), 3181 (DONE, 6/13), 3187 (DONE, 6/12), 3189 (DONE, 6/8), and 3201 (DONE, 6/13)
4. 3203 (DONE, 6/12), 3205 (DONE, 6/12)
5. 3125, 3127, 3129 (DONE, 7/11), 3027, 3130, 3132 (DONE, 6/18)
6. 3071, 3073 (DONE, 6/23), 3077/3079/3081 (DONE, 7/20), 3085 (DONE, 6/30), 3087 (DONE, 7/17)
7. 3170/3168 (DONE, 7/8), 3162 (DONE, 7/1), 3160 (DONE, 6/30), 3167 (DONE, 6/25), 3165 (DONE, 7/10)
8. 3084 (DONE, 7/25), 3082 (DONE, 7/27), 3078 (DONE,7/28), 3076 (DONE, 7/30, 3074 (DONE, 7/31)
9. 3206/3204/3202 (DONE, 8/1), 3214/3212/3210 (DONE, 8/4)