The following is a list of the projects currently being worked and/or considered by the HOA for the next several years. The priority and timing of the projects are heavily dependent on the budget. At any point, the priority may change due to a variety of factors.
| Project | Reason | Estimated start date | Start date | Estimated completion |
|---|---|---|---|---|
| Gutter cleaing | To protect roofs and homes | December of 2025/January of 2026 | ||
| Trim large tree branches over houses | To protect roofs/gutters and mitigate moss buildup | Spring of 2026 | ||
| Trim small limbs over roofs | To protect roofs/gutters and mitigate moss buildup | Spring of 2026 | ||
| Replace rotted fascia, paint all fascia, paint all wood replaced during roofing project | To protect home value | Summer of 2026 | ||
| Repair/replace gutters | To protect the roofs | Summer of 2026 or 2027 | ||
| Paint parking spaces in guest parking | To help alleviate parking issues | Summer of 2026 | ||
| Irrigation system audit | Reduce wasted water and improve watering efficiency | 2025/2026 | 2025 | Summer of 2026 |
| Extend downspouts into gutters | To protect the roofs by preventing water damage and moss buildup | 2026 or 2027 | ||
| Replace rotted fencing | Aesthetics, home value | 2028-2030 |
Completed projects in 2025:
| Project | Completed |
|---|---|
| Guest parking signs | October of 2025 |
| Wood chips | June-October of 2025 |
| New landscaping company | October of 2025 |
| Roof replacement | May-August of 2025 |
| Tree branch trimming | May-June of 2025 |
| New property management company | May-June of 2025 |