The following is a list of the projects currently being worked and/or considered by the HOA for the next couple of years. The priority and timing of the projects is heavily dependent on the budget. At any point, the priority may change due to various factors.
Project | Reason | Estimated start date | Start date | Estimated completion |
---|---|---|---|---|
Replace roofing | Roofs are end of life | Summer of 2025 | May of 2025 | September of 2025 |
Replace rotted fascia, paint all fascia, paint all wood replaced during roofing project | To protect roofs and the homes | Summer of 2025? or Summer of 2027 | ||
Trim tree branches over houses | To protect roofs/gutters and mitigate moss buildup | Spring of 2026 | ||
Repair/replace gutters | To protect the roofs | 2026 | ||
Extend gutters that run onto roofs into gutters | To protect the roofs by preventing water damage and moss buildup | 2026 | ||
Barkchips | Soil health, moisture retention, and aesthetics | Summer/fall of 2025 |